Chamic Industrial Services Ltd will be continually adding case studies to this page, showing our team at work and detailing the work we have done. We operate as a demolition expert and asbestos contractor all across Scotland and Northern England.
Quality is at the forefront of everything Chamic Industrial Services Ltd do. This is why we have been the preferred partner for many well known institutions and organisations over the years.
Based in Edinburgh, we provide site clearances, demolition and asbestos removal and disposal all across Scotland and Northern England. If you need an experienced demolition and asbestos contractor, please check out our qualifications, then get in touch.
Whatever the size of your project, Chamic Industrial Services Ltd has the skills and experience to help. For professional advice and to arrange a quotation, contact us at: reception@chamic.co.uk
Description:
This project Chamic was appointed to carry out the Internal Down takings work causing minimal disruption to the prestigious live hotel on the world-famous golf course. The works were carried out Monday to Friday and noisy works such as blockwork wall demolition were commenced after 10am as to not disrupt hotel guests.
This was delivered successfully on time, with daily progress meetings with the Main Contractor due to the sensitive nature of a live hotel.
Client:
Sharkey
Location:
St Andrews
Dates:
December 2019 – October 2020
Duration:
38 Weeks
Value:
£255,000.00
Description:
This project Chamic was appointed to carry out the demolition/recycling work causing minimal disruption to the adjoining housing. The main works were carried out with our plant including JCB 220 with Hammer Shear attachment, JCB 150 with Hydraulic Hammer and a Mobile Crusher. The full works comprised:
Using a vortex machine to dampen the area during demolition/crushing works this minimised dust and disruption to neighbours and local businesses. This was delivered successfully on time and on budget.
Client:
Confidential
Location:
Edinburgh
Dates:
September 2019 – January 2020
Duration:
12 Weeks
Value:
£100,000.00 +
Description:
This project Chamic was appointed to carry out the full Asbestos Removal Works and Demolition Enabling Works. Working closely together the Asbestos/Demolition team meticulously planned the works so the project ran smoothly, and areas were available to carry out works, so the programme was met.
The full works comprised:
This project was in a highly sensitive area situated on Princes Street, Edinburgh Chamic overcame this by housing the Asbestos Decontamination Unit internally and coordinating skips for waste removal on a wait and load basis. This was all taken on board at the planning stage allowing the project to be handed over on time and within budget.
Client:
Parabola
Location:
Edinburgh
Dates:
January 2019 – June 2019
Duration:
26 Weeks
Value:
£552,00.00
Description:
Removal and disposal of asbestos containing materials from various locations within the building located on George Street. The City Centre location meant Chamic had to house the decontamination facilities internally and co-ordinated skips for waste removal on a wait and load basis in the early hours prior to offices and shops opening.
Client:
Knight Frank
Location:
Edinburgh
Dates:
January 2021 – March 2021
Duration:
12 Weeks
Value:
£120,000.00
Description:
Removal and disposal of asbestos containing materials from various locations within the listed building prior to commencement of the refurbishment work.
Various items had to be de-contaminated and preserved for further use within the University Music Department.
The project was within a historic listed building with various items having to be decontaminated and preserved for future use for the University’s prestigious music department.
Client:
Taylor & Fraser
Location:
St Andrews
Dates:
May 2021 – August 2021
Duration:
10 Weeks
Value:
£180,000.00
Description:
Removal and disposal of the concrete flooring and contaminated soil within the solum area of the kitchen with fully controlled conditions to allow new drainage pipework to be installed in the primary school. The school was fully operational throughout the works being completed.
Client:
East Lothian Council
Location:
Tranent
Dates:
May 2021 – June 2021
Duration:
6 Weeks
Value:
£70,000.00